Jlt Office Fit Out

JLT Office Fit-Out

location-icon

LOCATION

170 Railway Parade, West Leederville
architect-icon

ARCHITECT

HBO+EMTB
project-icon

TYPE OF PROJECT

Construction
value-icon

VALUE

$3.5 million (incl. GST)
status-icon

STATUS

Completed
Jlt Office Fit Out

PROJECT SNAPSHOT

This project comprised of a contemporary 3,000m² office fit-out over two floors. Features included a front-of-house reception area, adjacent client function space, open work areas, shared meeting zones, and quiet rooms.

OVERCOMING CHALLENGES

  • It was identified that maximum cost-effectiveness could be achieved through developing the office fit-out and building the base of 170 Railway Parade concurrently. Once the generic aspects of the base building had been completed, the remaining project fit-out was then integrated with JLT’s footprint (such as meeting rooms and staff hubs) and overall requirements. This process simultaneously maximised the use of trades and labour, minimised environmental impacts and eliminated double-ups that would often occur when components from the base build have to be removed because the client or tenant doesn’t require them. This tandem approach required meticulous planning with subcontractors and quick thinking from our team.
  • The contract was priced and executed on a drawings and specification basis. Although originally fully designed by the client, some aspects of the structure and services were redesigned by the design team to achieve cost savings and buildability advantages. This meant the job required multiple re-prices to meet the budget while still maintaining our program. Interior designers HBO+EMTB drove most of the design changes, leading to the challenge of maintaining momentum on site with every change and subsequent re-price.

HIGHLIGHTS

  • As the fit-out was an integrated one, work began early on the design so it could be incorporated into the works as the building progressed. Once this design integration took place, the work was incorporated into the program and the result was a 3,000m² fit-out delivered only three weeks after the completion of the base build.

FEATURES OF DEVELOPMENT

Utilising our outstanding fit-out capabilities, our team optimised aesthetics and balanced a neutral canvas with colourful feature paint and carpet, applied graphics and bright furniture.

Gallery

Team Involve with this Project

TEAM INVOLVED WITH THIS PROJECT

LATEST NEWS